Most estimators get the scale wrong but the relative estimates right. Everything takes longer than expected, because the estimate didn’t account for bug fixing, committee meetings, coffee breaks, and that crazy boss who interrupts all the time. This common estimator has very consistent velocities, but they’re below 1.0. For example, {0.6, 0.5, 0.6, 0.6, 0.5, 0.6, 0.7, 0.6}
Author | Joel Spolsky |
Work | Evidence Based Scheduling |